Creating a Realistic Schedule for Your New Pension Administration Solution (PAS)

By: Jeffrey Mills and Meir Schecter, Segal

The starting point for most project schedules is a vendor's proposal. According to Segal data, these projects go 44% longer than originally planned by the vendor. In this article, we discuss how to address this during the procurement process and jointly prepare and remain accountable for project extensions.

This is an excerpt from NCPERS Spring 2024 issue of PERSist, originally published April 25, 2024.

In the Spring 2023 issue of PERSist, Laurie Mitchell of Tegrit Software Ventures, Inc. provided some sage advice about how to prepare for your new pension administration solution (PAS). We'd like to add another preparation item to Ms. Mitchell's list: Prepare yourself for how long your PAS will take. Replacing your PAS will likely take longer than what your selected vendor proposed. Depending on the size of your pension office, it could take significantly longer.

Understanding the likely duration of your project allows you to manage these aspects effectively:

  • Budgeting. You'll be better able to predict the project's budgetary needs.

  • Staffing. You'll be able to anticipate the amount of time needed to backfill for those staff members supporting the project.

  • Stakeholder communications. You can communicate the project status with confidence — and avoid the pain of making prediction after prediction that doesn't work out as planned

How much longer than originally scheduled do PAS replacement projects typically take?
Based on Segal's experience with 35 public sector PAS replacement projects in recent years, on average, the projects took 44% longer than originally planned.

It is important to note that this data should not be interpreted as meaning that these projects took longer than they should have taken — only, that they took longer than they were originally proposed to take.

What is the root cause of this experience?
It is tempting to attribute this experience to the “planning fallacy,” a phenomenon which predictions about how much time will be needed to complete a future task (project) are biased by optimism. Consequently, the actual amount of time needed is underestimated.

Although the planning fallacy may be partially responsible, it is our opinion that the longer-than-planned duration of PAS replacement projects is primarily caused by an indirect “procurement incentive.” The nature of the public sector procurement process is to publish, as part of the procurement documents (RFPs), the criteria against which vendor proposals will be evaluated. “Cost,” a direct function of duration, is always one of the evaluation criteria, and typically represents at least 20% of the total evaluation. As such, responding vendors are incentivized to propose an aggressive timeline, to keep their bid low. Furthermore, the vendor likely anticipates they will be evaluated poorly by proposing a longer schedule, even if it more realistic.

How can the situation be managed?
Short of structurally changing the procurement process, we don't believe there is a simple way to prevent this situation, but there is a way to manage it.

We start with a premise that we believe to be almost always true: The responsibility for project extensions is shared between the client and its vendor, and assessing the responsible party for any project delay is complex and often contentious.

It is our recommendation to perform the procurement process, as follows:

  • Do not evaluate the cost of a vendor proposal until the proposal is deemed acceptable from a functional/ technical perspective.

  • Evaluate cost and select a leading vendor with whom you will attempt to reach a contractual agreement.

  • Discuss and clarify the assumptions used by the vendor to create the proposed schedule, including asking for their project duration history and understanding their expectations of your staff availability and capabilities.

  • Ask the vendor for a best and final offer that represents the project duration and cost that aligns with their history and the revised assumptions.

  • As part of the contract, negotiate the additional fees to be paid to the vendor for project extensions (not caused by additional client-requested functionality) in such a way as to incentivize the vendor, and the client, to minimize project extensions.

Although no one desires a long project, being realistic about what is likely to happen helps you to manage the project more effectively.

About the Authors
Jeffrey S. Mills, PMP is a Vice President and Leader of Segal's Administration and Technology Consulting (ATC) Practice. Jeff has more than 20 years of experience providing operational and technology consulting to benefit plans and specifically related to public pension administration system projects. 
Meir Schecter is a Senior Consultant in Segal's ATC practice. Meir has been consulting in the public sector pension arena for over 15 years. Prior to that, he consulted in the private sector employee benefit space— including pensions—for 20 years.

Comments

There have been no comments made on this article. Why not be the first and add your own comment using the form below.

Leave a comment

Please complete the form below to submit a comment on this article. A valid email address is required to submit a comment though it will not be displayed on the site.

HTML has been disabled but if you wish to add any hyperlinks or text formatting you can use any of the following codes: [B]bold text[/B], [I]italic text[/I], [U]underlined text[/U], [S]strike through text[/S], [URL]http://www.yourlink.com[/URL], [URL=http//www.yourlink.com]your text[/URL]

Contributors